BUSINESSES SHOULD RESPECT AND MAKE EFFORTS TO PROTECT AND RESTORE THE ENVIRONMENT

We view climate action as a business imperative and a moral responsibility. Recognizing the far-reaching impacts of climate change, we are accelerating our transition toward a net-zero future. We are decarbonizing our operations through renewable energy, improving energy efficiency, and reducing carbon emissions by reimagining our materials and supply chains. Our efforts on water conservation and waste recycling are note worthy and our journey towards sustainable development is resolute.

Gross Scope 1 Emission

537KgCO2/tonne of cementitious material

0%

Renewable and green energy used

0x

Water Positive

0 million tonnes

of waste derived resource consumed

Essential Indicators

Parameter
UOM
FY 2024-25
(Current Financial Year)
FY 2023-24
(Previous Financial Year)
From renewable sources (in Giga Joules)
Total electricity consumption (A)
GJ
439,920
194,170
Total fuel consumption (B)
GJ
5,747,832
4,633,771
Energy consumption through other sources (C)
GJ
0
0
Total energy consumed from renewable sources (A+B+C)
GJ
6,187,752
4,827,941
From non-renewable sources (in Giga Joules)
Total electricity consumption (D)
GJ
2,440,800
2,961,536
Total fuel consumption (E)
GJ
63,865,773
62,541,366
Energy consumption through other sources (F)
GJ
0
0
Total energy consumption (D+E+F)
GJ
66,306,573
65,502,902
Total energy consumed (A+B+C+D+E+F)
GJ
72,494,325
70,330,843
Energy intensity per rupee of turnover (Total energy consumption/Revenue from operations)
` of turnover
0.0003
0.0003
Energy intensity per rupee of turnover adjusted for Purchasing Power Parity (PPP)
GJ/USD PPP adjusted
0.0079
0.0081
Energy intensity in terms of physical output
GJ/tonne of cementitous material
2.6
2.6
Energy Intensity (optional)- the relevant metric may be selected by the entity
NA
NA

Note: Indicate if any independent assessment / evaluation / assurance has been carried out by an external agency? (Yes/No) If yes, name of the external agency.
Yes, TUV India Private Limited

Yes, Maratha, Suli, Rauri, Ambujanagar, Ropar, Rabariyawas, Bhatapara & Sankrail are the Designated Consumers. All the designated consumers have achieved their PAT Target except for Suli & Rauri. Suli & Rauri achieved PAT target by purchasing ESCerts.

Parameter
UOM
FY 2024-25
(Current Financial Year)
FY 2023-24
(Previous Financial Year)
Water withdrawal by source (in kilolitres)
(i) Surface water
KL
323,346
374,806
(ii) Groundwater
KL
1,232,245
1,892,104
(iii) Third party water
KL
350,724
71,170
(iv) Seawater / desalinated water
KL
0
0
(v) Others (Rain Water Harvested)
KL
2,796,782
3,306,306
Total volume of water withdrawal for cement manufacturing
(in kilolitres) (i + ii + iii + iv + v)
KL
4,703,097
5,644,386
Total volume of water consumption for cement manufacturing
KL
4,703,097
5,644,386
Water intensity per rupee of turnover
(Total energy consumption/ Revenue from operations)
Litres/ ` of turnover
0.025
0.031
Water intensity per rupee of turnover adjusted for Purchasing Power Parity (PPP) (Total water consumption / Revenue from operations adjusted for PPP)
Litre/ USD PPP adjusted
0.5
0.7
Water intensity in terms of physical output
Liters / tonne of cementitious material
172
206
Water intensity (optional) – the relevant metric may be selected by the entity
NA
NA

Note: Indicate if any independent assessment / evaluation / assurance has been carried out by an external agency? (Yes/No) If yes, name of the external agency.
Yes, TUV India Private Limited

Parameter
FY 2024-25
(Current Financial Year)
FY 2023-24
(Previous Financial Year)
Water discharge by destination and level of treatment (in kilolitres)
(i) To Surface water
No treatment
0
0
With treatment-please specify level of treatment
0
0
(ii) To Groundwater
No treatment
0
0
With treatment – please specify level of treatment
0
0
(iii) To Seawater
No treatment
0
0
With treatment – please specify level of treatment
0
0
(iv) Sent to Third Parties (Municipal STP)
No treatment
0
0
With treatment – please specify level of treatment
0
0
(v) Others
No treatment
0
0
With treatment – please specify level of treatment
0
0
Total water discharged (in kilolitres)
0
0

Note: Indicate if any independent assessment/ evaluation/assurance has been carried out by an external agency? (Yes/No) If yes, name of the external agency.
Yes, TUV India Private Limited

Zero Liquid Discharge is implemented at all plant locations. No waste water/ treated waste water is discharged outside the plant premises.

Parameter
Please specify unit
FY 2024-25
(Current Financial Year)
FY 2023-24
(Previous Financial Year)
NOx
Tonnes
11,608
12,277
SOx
Tonnes
1,289
1,343
Particulate matter (PM)
Tonnes
362
367
Persistent organic pollutants (POP)
NA
NA
NA
Volatile organic compounds (VOC)
NA
NA
NA
Hazardous air pollutants (HAP)
NA
NA
NA
Others – please specify
NA
NA
NA

Note: All our plants meet with the prescribed standards given by respective regulatory body.

Note: Indicate if any independent assessment / evaluation / assurance has been carried out by an external agency? (Yes/No) If yes, name of the external agency.
Yes, TUV India Private Limited

Parameter
Unit
FY 2024-25
(Current Financial Year)
FY 2023-24
(Previous Financial Year)
Total Scope 1 emissions (Break-up of the GHG into
CO2, CH4, N2O, HFCs, PFCs, SF6, NF3, if available)
tonnes of CO2
14,756,978
15,286,295
Total Scope 2 emissions (Break-up of the GHG into
CO2, CH4, N2O, HFCs, PFCs, SF6, NF3, if available)
tonnes of CO2
485,448
589,017
Total Scope 1 and Scope 2 emissions per rupee
of turnover (Total Scope 1 and Scope 2 GHG
emissions/Revenue from operations)
Kg CO2/` of turnover
0.08
0.09
Total Scope 1 and Scope 2 emissions per rupee
of turnover adjusted for Purchasing Power Parity
(PPP) (Total Scope 1 and Scope 2 GHG emissions/
Revenue from operations adjusted for PPP)
Kg CO2/ USD PPP adjusted
1.6
1.7
Total Scope 1 and Scope 2 emission intensity
in terms of physical output
Kg CO2/tonne
of cementitious
material
555
581
Total Scope 1 and Scope 2 emission intensity (optional)
– the relevant metric may be selected by the entity
NA
NA

Note: Indicate if any independent assessment / evaluation / assurance has been carried out by an external agency? (Yes/No) If yes, name of the external agency.
Yes, TUV India Private Limited

The Company is committed to reduce its carbon footprint. It is a signatory to SBTi to be Net Zero by 2050. The 2030 GHG emission reduction targets are validated by SBTi. The Company has taken multiple initiatives to reduce greenhouse gases. These include: 1) Improved technology 2) Energy efficiency 3) Use of renewable energy 4) Use of green energy like WHRS 5) Use of alternate fuels 6) Use of alternate raw materials 7) Reduction in clinker factor and having larger share of blended products in its portfolio.

Parameter
Unit
FY 2024-25
(Current Financial Year)
FY 2023-24
(Previous Financial Year)
Total Waste generated (in metric tonnes)
Plastic waste (A)
MT
27,195
36,533
E-waste (B)
MT
32
30
Bio-medical waste (C)
MT
1
0.5
Construction and demolition waste (D)
MT
0
54
Battery waste (E)
MT
35
29
Radioactive waste (F)
MT
0
0
Other Hazardous waste. Please specify, if any. (G)
MT
345
1,743
Other Non-hazardous waste generated (H).Please specify, if any. (Non hazardous waste contain Flyash, MS Scrap, Wooden Scrap, Metal Drum, Paper, etc)
MT
256,942
247,724
Total (A+B + C + D + E + F + G + H) in metric tonnes
MT
283,851
286,145
Waste intensity per rupee of turnover
Kg/` of turnover
0.0016
0.002
Waste intensity per rupee of turnover adjusted for Purchasing Power Parity (PPP) (Total waste generated/Revenue from operations adjusted for PPP)
kg/ USD PPP adjusted
0.031
0.033
Waste intensity in terms of physical output
Kg/tonne of cementitious material
10.34
10.46
Waste intensity (optional) – the relevant metric may be selected by the entity
NA
NA
NA
For each category of waste generated, total waste recovered through recycling, re-using or other recovery operations (in metric tonnes)
Category of waste
(i) Recycled
MT
283,850
284,371
(ii) Re-used
MT
0
0
(iii) Other recovery operations
MT
0
0
Total
MT
283,850
284,371
For each category of waste generated, total waste disposed by nature of disposal method (in metric tonnes)
Category of waste
(i) Incineration
MT
1
1,744
(ii) Landfilling
MT
0
0
(iii) Other disposal operations
MT
0
0
Total
MT
1
1,744

Note: Indicate if any independent assessment / evaluation / assurance has been carried out by an external agency? (Yes/No) If yes, name of the external agency.
Yes, TUV India Private Limited

The Company adheres to the principles of sustainable consumption of resources while reducing waste generation and complying with the tenets of circular economy. The Company minimises waste disposal through maximising recycling and reusing efforts. The Company also ensures proper disposal of E-waste, biomedical waste, scrap, etc. through authorised recyclers registered with the regulatory agencies.

Our waste management initiatives include:

  • Plastic waste is mainly disposed of through co-processing, with a minimal amount of burst bags disposed of through authorised scrap dealers.
  • Biomedical waste is incinerated at authorised Common Biomedical Waste Treatment Facilities.
  • E-waste is recycled through authorised recyclers.
  • Hazardous waste (used oil, discarded drums) is either reused in plants or co-processed in cement kilns, with non-co-processable quantities sent to a common authorised facility.
  • Scraps are sold to authorised vendors.
  • Mining overburden is repurposed for backfilling within the mines.

S. No.
Type of operations
Whether the conditions of environmental approval/clearance are being complied with? (Yes/No) If no, the reasons thereof and corrective action taken, if any
Nil
Nil
Yes

S. No.
Name and brief details of project
EIA Notification No.
Date
Whether conducted by independent external agency (Yes/No)
Results communicated in public domain (Yes/No)
Relevant Web link
1.
Bathinda GU expansion 1.20 MTPA to 2.2 MTPA located near Guru Nanak Dev Thermal Power Plant, Malout Road, Village- Malout, Tehsil & District Bathinda of Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
EC granted on 17.07.2024
Yes
Yes
2.
Proposed expansion of Integrated Cement Plant - Clinker (2.4 million TPA to 3.5 million TPA)-Cement (Existing 3.6 million TPA-No change)- WHRB (7.5 MW to 12 MW) and CPP ( Existing 18 & 15 MW-No change)- by Installation of new Line-II (Rotary Kiln 2800 TPD) and new Fly Ash Dryer 1000 TPD at Village- Rabriyawas, Tehsil -Jaitaran, District - Pali, Rajasthan by M/s Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
EC granted on 02.11.2024
Yes
Yes
3.
Maratha Limestone Mine, ML - I (ML Area – 579.90 ha) with Expansion in Limestone Production Capacity from 1.5 million TPA to 3.5 million TPA, at Villages- Thutra and Lakhmapur (Tehsil: Korpana) and Hirapur, Isapur and Sonapur (Tehsil: Rajura), District Chandrapur, State: Maharashtra of M/s Ambuja Cements Ltd.
S.O. 1533(E)
dated
14.09.2006
& its
amendments
EC applied on 26.08.2024
Yes
Yes
4.
Proposed Naulatha Cement Grinding Unit with Cement Production capacity of 1 x 4.0 Million MTPA at Village: Naulatha, Tehsil: Israna, District: Panipat, Haryana by M/s. Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
EC applied on 22.01.2025
Yes
Yes
5.
Proposed 3D2 Limestone Block (Auctioned Block) (Area: 434.08502 ha) with Proposed Limestone Production Capacity 3.0 Million TPA, OB/waste 1.15 Million TPA, Top Soil 0.34 Million TPA, (Total Excavation 4.49 Million TPA) along with Installation of Crusher (2000 TPH) with Wobbler at Villages: Harima & Sarasani, Tehsil and District: Nagaur, Rajasthan by Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
EC applied on 17.02.2025
Yes
Yes
6.
Proposed Standalone Cement Grinding Unit with Cement Production of 6.0 MMTPA (2X3.0 Million Metric Tons per Annum) located at Village- Ramannapet, Taluka-Ramannapet, District: Yadadri Bhuvanagiri, State- Telangana by M/s. Ambuja Cements Limited (ACL)
S.O. 1533(E)
dated
14.09.2006
& its
amendments
EC applied on 13.03.2025
Yes
Yes
7.
Expansion of Integrated Cement (Clinker: 8.1 MTPA to 16.1 MTPA, Cement: 6.5 MTPA to 16.5 MTPA, WHRS: 43 MW to 85 MW & CPP: 63 MW to 123 MW) by Installation of Line- IV & Line-V at Village: Rawan, Tehsil: Balodabazar, District: Balodabazar-Bhatapara, State: Chhattisgarh by M/s Ambuja Cements Limited (Unit: Bhatapara)
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH completed on 08.01.2025
Yes
Yes
8.
Proposed Expansion in production capacity of Cement Grinding Unit from 1.2 MTPA to 3.0 MTPA at located near Village: Lakeshwari, P.O- Sikanderpur Bhainswal, Bhagwanpur, Roorkee, Distt. Haridwar, Uttarakhand, Pin- 247661 by M/s Ambuja Cements Limited (Unit: Roorkee)
S.O. 1533(E) dated
14.09.2006
& its
amendments
PH completed on 18.01.2025
Yes
Yes
9.
Expansion in Limestone Production Capacity from 2.0 Million TPA to 6.3 Million TPA, (ROM 6.5 Million TPA including 0.2 Million TPA screen rejects), Sub Grade 1.7 Million TPA, Top Soil 0.27 Million TPA, Waste 2.55 Million TPA (Total Excavation 11.02 Million TPA) with existing crusher of 1800 TPH with screen and a proposed crusher of 1800 TPH capacity in Maldi Mopar Limestone Mine (ML Area – 553.656 ha) in Villages- Boirdih, Karmandih ,Maldi, Mopar and Devrani Tehsil: Balodabazar Bhatapara, Chhattisgarh by M/s. Ambuja Cements Limited
S.O. 1533(E) dated
14.09.2006
& its
amendments
PH completed on 20.01.2025
Yes
Yes
10.
Proposed Cement Grinding Unit with Cement Production Capacity of 2 x 3 Million Metric Tons per Annum (6.0 MMTPA) at located Village: Devli, Tehsil+ District: Palwal, State: Haryana by M/S. Ambuja Cements Limited
S.O. 1533(E) dated
14.09.2006
& its
amendments
PH completed on 30.01.2025
Yes
Yes
11.
Expansion in Limestone Production Capacity from 2.0 Million TPA to 3.5 Million TPA, Top Soil 0.25 Million TPA, Waste (OB/IB) 2.40 Million TPA, Sub grade 0.50 Million TPA (Total Excavation 6.65 Million TPA) along with existing crusher of 1200 TPH in Maratha Limestone Mine - II (ML Area – 880.31 ha) in Villages- Bakhardi, Upparwahi, Chandur, Pimpalgaon, Lakhmapur and Thutra (Tehsil: Korpana) and Sonapur (Tehsil: Rajura), District- Chandrapur, State: Maharashtra by M/s. Ambuja Cements Limited
S.O. 1533(E) dated
14.09.2006
& its
amendments
PH completed on 03.02.2025
Yes
Yes
12.
Kodidra Block Mining Lease for Limestone and Marl major Mineral for 1.5 million TPA production over an area of 41.31.86 Ha. located in Kodidra Village, Veraval Taluka, Gir-Somnath District, Gujarat State of M/s Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH completed on 17.03.2025
Yes
Yes
13.
Kukaras Block (Private) Mining Lease for Limestone and Marl Mineral for 2.0 milllion TPA production of Limestone over an area of 29.16.81 Ha located in Village: Kukaras, Taluka: Veraval, District: Gir-Somnath, State: Gujarat, by M/s Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH completed on 17.03.2025
Yes
Yes
14.
"Proposed Greenfield Project Of Standalone Grinding Unit With Cement Production Capacity Of 6 Mmtpa (2 X 3 Mmtpa) At Village-Malkhed & Udkhed, Taluka-Chandur Railway & Amravati, District- Amravati, Maharashtra By M/S. Ambuja Concrete North Private Limited"
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH completed on 27.03.2025
Yes
Yes
15.
Proposed Ambivli Cement Grinding Unit With Production Capacity Of 2 X 3 Mmtpa (6.0 Mmtpa) Located At Village: Ambivli, Taluka: Kalyan, District: Thane, State: Maharashtra by M/s. Ambuja Concrete North Private Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH to be conducted
Yes
Yes
Draft EIA/ EMP Report submitted to competent authorities of MPCB. https://mpcb.gov.in/
16.
Proposed Greenfield project of Standalone Grinding Unit with Cement production capacity of 2 x 3 MMTPA (6 MMTPA) at Village-Bornar, Taluka & District-Jalgaon, Maharashtra by M/s. Ambuja Concrete North Private Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH to be conducted
Yes
Yes
Draft EIA/EMP Report to be submitted to competent authorities of MPCB. https://mpcb.gov.in/
17.
Proposed expansion in integrated cement plant (Clinker: 3.0 MTPA to 15.06 MTPA, Cement: 4.5 MTPA to 14.5 MTPA, CPP: 50 MW (No Change), WHRS 15 MW to 87 MW, DG Set (9190 kVA), AFR Pre-processing & Feeding System (4250 TPD), Synthetic Gypsum Plant (5000 TPD) and Fly Ash Dryer: 1000 TPD, Railway siding with Wagon Tippler & Loader by Installation of new Line – 2, 3 & 4 and Plant Residential Colony located at Village & Tehsil: Marwar Mundwa, District: Nagaur, State Rajasthan of ACL
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH to be conducted
Yes
Yes
Draft EIA/ EMP Report submitted to competent authorities of MPCB. https://environment.rajasthan.gov.in/
18.
Marwar Mundwa Limestone(ML-I) with enhancement in Production Capacity from 3.0 to 14.0 MTPA in the Mine Lease area of 699.99 Ha (ML No. 111/2007) by M/s Ambuja Cement Limited located near to village Rupasar, Inana, Mundwa, and Bhadana, Tehsil Mundwa, District Nagaur, State Rajasthan of M/S Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH to be conducted
Yes
Yes
Draft EIA/ EMP Report submitted to competent authorities of MPCB. https://environment.rajasthan.gov.in/
19.
Expansion in Marwar Mundwa Limestone (ML-II) for Production Capacity from 2.0 to 4.5 Million TPA in the Mine Lease Area of 635 ha (ML-03/1994) by M/s Ambuja Cement Limited located at Villages Kherwad, Rupasar, and Didyakalan, Tehsil Jayal and Nagaur, Rajasthan of M/S Ambuja Cements Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH to be conducted
Yes
Yes
Draft EIA/ EMP Report submitted to competent authorities of MPCB. https://environment.rajasthan.gov.in/
20.
Proposed Standalone Grinding Unit with Cement Production Capacity of 4.0 Million TPA (2 x 2.0 Million TPA) at Village: Mawan, Tehsil & District: Guna, Madhya Pradesh by M/s. Ambuja Concrete North Private Limited
S.O. 1533(E)
dated
14.09.2006
& its
amendments
PH to be conducted on 25.04.2025
Yes
Yes
Draft EIA/ EMP Report submitted to competent authorities of MPCB. https://mppcb.mp.gov.in/

S. No.
Specify the law / regulation / guidelines which was not complied with
Provide details of the non-compliance
Any fines / penalties /action taken by regulatory agencies such as pollution control boards or by courts
Corrective action taken, if any
1
Air Act (Prevention and controlof pollution) 1981
Emission due to rupturing of pre-heater duct in Rauri Plant
6.6 Lakh
Repaired the duct and emission controlled